Compton College – Central Plant & Utility Infrastructure Ph. 1
Project Delivery Method: Design-Bid-Build

Contract Value: $27,650,000

Status: Completed in 2014

Project Description: The College will receive a new 12,000 SF central plant and a major utility upgrade as a result of the development of this project.  A new 5KV main electrical switch gear, stadium lighting, solar panels, a detention pond as well as a re-designed entrance to the campus from Artesia Boulevard are also included in the scope of work.

Design Team Lead:  S & K Engineers